A Platform for Success

Jaguar Land Rover, Paintshop Upgrade, Castle Bromwich

Jaguar Land Rover, Paintshop Upgrade, Castle Bromwich

Godiva was responsible for the design and erection of industrial scaffolding services to enable the two new TAR units to be positioned on the new platform within the JLR Paintshop. A seven metre high scaffolding platform was erected to allow the new TAR units to be manoeuvred through a hole in the Paintshop exterior wall and across scaffolding platforms built above the Paintshop interior. Erection works were undertaken in advance of the weekend shut-down outside normal hours working overnight, in order to minimise disruption to normal Paintshop production.

Client: Jaguar Land Rover
Prime Contractor: DURR
Scaffolding Contractor: Godiva Access & Scaffolding

Value: £100,000